The 35GWh lithium-ion cell production facility for electric vehicles by Tesla Motors and Panasonic will bring only a modest reduction in battery costs, according to Lux Research. It is also expected that the Gigafactory will create significant overcapacity, given that Tesla will likely not meet its target of selling 500,000 EVs in 2020.
Tesla and its partner, Panasonic, will contribute about 45 per cent and 35 per cent, respectively, of the initial $4 billion required to build the Gigafactory, proposed to go on-stream in 2017. An analysis by Lux Research projects sales of only 240,000 cars in 2020, leading to razor-thin margins to Panasonic and 57 per cent overcapacity.
"The Gigafactory will only reduce the Tesla Model 3's cost by $2,800, not enough to sway the success of the planned lower-cost EV," said Cosmin Laslau, Lux Research Analyst and the lead author of the report titled, "The Tesla-Panasonic Battery Gigafactory: Analysis of Li-ion Cost Trends, EV Price Reduction, and Capacity Utilization."
"Besides, Lux's analysis reveals significant overcapacity because Tesla will miss its ambitious target of half a million," he added.
Lux Research evaluated Tesla Motors' Gigafactory plan and its consequences for the EV industry. Among their findings:
Cost-cutting is the name of the game, but the Gigafactory does not do enough. Battery prices need to fall dramatically if plug-in cars hope to break beyond their current niche. The OEMs backing the U.S. Advanced Battery Consortium are targeting $125/kWh by 2020—more than four times lower than $520/kWh, the price Ford paid for its Focus EV battery packs. Currently, Tesla has the lowest cost—about $274/kWh, according to Lux Research analysis. Tesla founder Elon Musk aims to cut cost by 30 per cent, on the strength of scale, location, and technology, lowering the price to $196/kWh with the Gigafactory.
Panasonic faces risks. The Gigafactory might seem like a great win for Panasonic, ahead of rivals such as Samsung SDI, LG Chem, and NEC. But in reality the Japanese company faces high risks. In the optimistic scenario of Tesla attaining its targeted half a million EVs, Panasonic could rake in more than $15 billion between 2017 and 2020. But at the more likely 240,000 EVs, as estimated by Lux Research, Panasonic would take in only $7 billion on its likely investment of $1.4 billion, with questionable margins.
Gigafactory will lead to huge overcapacity. The Gigafactory, proposed to be built at a cost of $5 billion, is designed to make 35GWh Li-ion cells for half a million EVs. But in the likely event of much lower sales of 240,000, overcapacity will be to the extent of 20GWh. This 57 per cent overcapacity is unlikely to be filled either by rival carmakers or Tesla's own plans to sell some stationary battery packs to developers like SolarCity for residential photovoltaic integration and other uses.